top of page
Scott Henriksen

December 26 - January 2

Crews will be working December 27, 28, 29 and January 2.


  • Crew A - Crews will continue to work on 450 North. The road will be closed between 100 East and 300 East. This area will be closed for approximately 1 more week.

  • Crew B - Crews are continuing to work on 200 South. 200 South will be closed between 100 West and Main Street. This area will be closed for approximately 2 more weeks. After the new year, they will continue to work on 200 South and cross Main Street.

  • Crew C - Crews will be starting to work on 200 North between 100 East and 200 East.

  • Crew D - Crews will begin work on 400 North between Main and 100 East after the New Year. This area will be closed to through-traffic while this work is being completed.

  • Crew E - Crews are continuing to work in Hyrum installing pipe near 4400 South, between 700 West and the highway.


ROAD CLOSURES

  • 200 North between 100 East and 200 East will be closed for approximately 3 more weeks

  • 400 North between Main Street and 100 East will be closed from January 2- to mid-January.

  • 200 South is closed between 100 West and Main Street. This closure is expected to last 1 weeks.

  • 450 North will be closed between Main Street and 300 East beginning Tuesday, November 28. This closure is expected to last 3 weeks. ALL traffic will need to use alternate routes.


If you have rock, gravel, or pavers in your parkstrip, it is recommended that you pull those back prior to construction crews working in your area.



Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.

7 views0 comments

Recent Posts

See All

Comments


bottom of page