April 3rd, crews will begin working on 550 East between 200 South and 300 South. This work will include a hard road closure at 300 South and 550 East. Residents who live in the work zone area (see map below) are advised to approach from the north side of work zone (via Mond-Aire or Providence).
Crews are continuing to work at the railroad tracks in Hyrum to install sewer casing pipe. Crews will be working in this area for the next month, weather dependent. Flagging operations are in place.
Road Closures in Effect
Beginning April 3rd, 550 East will be closed to through traffic between 200 South and 300 South.
1200 West in Hyrum is closed between 4300 South and 4700 South. Flag operations are in place.