Scott Henriksen

Week of January 5, 2025

CONSTRUCTION UPDATE


  • Crew A - Crews will be working on the sewer main line on 300 East between 200 South and 300 South.

  • Crew B - Crews will be working on the lateral lines on 350 South between 100 East and 200 East.

  • Crew C - Crews are working on the sewer main line on Canyon Road, access will be very restricted. There will be no canyon access until the end of February. Crews will work to accommodate traffic to this road, but it is recommended that residents park at the city park from 8:30 am - 5:30 p.m. daily.

  • Crew D - Crews will be working on the pressurized sewer line on 2900 South/100 South.

  • Crew E - Crews are placing sewer lateral lines in the Mondair neighborhood, south of 100 South.


Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.





ROAD CLOSURES


  • Canyon Road will be closed until the end of February.

  • 350 South will be closed until mid-January.

  • 2900 South/100 South will be closed until the end of January.


Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.