Week of March 30, 2025

  • Scott Henriksen
  • Mar 28
  • 1 min read

CONSTRUCTION UPDATE


  • Crew A - Crews will be working on the sewer lateral lines on 140 East and the sewer main line on 550 North.

  • Crew B - Crews will be working on the sewer lateral lines in multiple places on 300 South.

  • Crew C - Crews will be finishing work on the sewer main line on 200 East between 200 South and 300 South. When they are done on 200 East they will be moving to 100 East and 550 North (west of Main Street).

  • Crew D - Crews are working on the sewer lateral lines on 100 North, between Main street and 300 North.


Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.


ROAD CLOSURES


  • 140 East will be closed until late March

  • 100 North will be closed between Main and 300 East until early April

  • 300 South, in multiple locations, until late March

  • 200 East, between 200 South and 300 South, until mid March

  • 100 East, between 200 South and 300 South, until late March

  • 550 East, west of Main Street, until early April


Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.




 
 
 